What Are The Techniques For Connecting Stones With Different Materials?

When decorating, we will use a lot of materials. How do we use these materials when they are really combined? Then we’ll come to this article

Connection process of stone and stone

If the stone and stone are spliced on the same plane, it is necessary to do sealing, chamfering, dislocation, or closing strip, etc. it is not recommended to connect directly.

1. Material analysis

1)    The special dry hanging accessories for stone shall be selected from the specified stone processing and fixed frame, and fixed and installed with special AB glue for stone

2)    During installation, the anti-collision angle shall be 5 * 5mm, and the stone shall be protected on six sides

3)    Finish the surface treatment, wipe and clean the joints with special sealant, and use a special protective film for finished product protection

2. Detailed process

Preparation — site setting out — material processing — base course treatment — fixing of stone dry hanging structure frame — bonding with special AB glue for stone — paving stone — surface treatment

In addition, when there are external corners between stone and stone, a variety of edge treatment processes can be adopted, such as Begonia corner, French edge, grooving, etc., which can connect the stone well.

● Process practice of connecting stone and stainless steel

1. Connection process between stone and stainless steel (I)

When the splicing height of stainless steel and stone is not on the same line, pay attention to the front and rear blank holder relationship, and properly reserve process joints

Material analysis

1)    Make partition wall for square pipe, seal cement pressure plate, and reinforce the base to be treated

2)    Select customized stone processing, and process stainless steel, stainless steel, and stone closing

3)    The stone shall be fixed with special glue and protected on six sides

4)    Finish the surface treatment, wipe and clean the joints with special sealant, and use a special protective film for finished product protection

Construction procedure

Preparation — site setting out — material processing — fixing of partition structure frame — base course treatment — sealing cement pressure plate and fireproof plate — stainless steel customization — paving stone — installing stainless steel — finish surface treatment

2. Connection process between stone and stainless steel (II)

When the splicing height of stainless steel and stone is not on the same line, pay attention to the front and rear blank holder relationship, and properly reserve process joints. The protective film is not easy to tear off during stainless steel construction. The bonding thickness between stainless steel shape and wood base shall be about 3mm, and the flat plate shall be bonded with glass glue and universal adhesive.

Material analysis

1)    The stone structure frame is made of channel steel and galvanized angle iron, and the customized stone is selected for installation

2)    Stainless steel base course fabrication, wood keel, fireproof board, stainless steel installation

3)    The stone shall be fixed with special glue and protected on six sides

4)    Finish the surface treatment, wipe and clean the joints with special sealant, and use a special protective film for finished product protection

Construction procedure

Preparation — site setting out — material processing — dry hanging stone structure frame fixing — base treatment — making foundation with wood keel and fireproof board — stainless steel customization — dry hanging stone — installing stainless steel — finish surface treatment.

● Connection process of stone and glass

01 process practice of connecting stone and glass (I)

Foundation thickness treatment, fragile product installation needs professional guidance, and pay attention to customized dimensions (it is not suitable to be processed again on site)

Material analysis

  1. Customized stone, 8# square tube, 50 * 40 galvanized channel steel, galvanized dry hanger, fireproof board base course

2. Customized mirrors, stainless steel, etc. pay attention to closing the glass with the stone. The stone is fixed with special glue and needs to be protected on six sides

3. Finish the surface treatment, wipe and clean the joints with special sealant, and use a special protective film for finished product protection

Construction procedure

Preparation worksite setting out – material processing – fixing of partition structure frame – base treatment – dry hanging stone frame production – glass foundation production – dry hanging stone – glass installation – surface treatment

02. Process method of connecting stone and glass (II)

Material analysis

  1. Custom stone, ordinary portland cement with fine sand or coarse sand, wood keel, and fireproof plywood base

2. Customized mirrors, stainless steel, etc. pay attention to the closing of glass and stone, and six side protection is required

3. Finish the surface treatment, wipe and clean the joints with special sealant, and use a special protective film for finished product protection

Construction procedure

Preparation worksite setting out – material processing – base treatment – mirror and structural frame production – glass foundation production – cement mortar bonding layer – paving stone – installing glass – surface treatment

03. Connection process of stone and glass (III)

Material analysis

  1. Customized stone, stainless steel, mirror, galvanized angle steel, wooden keel, and fireproof splint

2. The stone is fixed with special AB glue and needs to be protected on six sides. The stainless steel edge is folded into a frame shape

3. Finish the surface treatment, wipe and clean the joints with special sealant, and use a special protective film for finished product protection

Construction procedure

Preparation work — On-site setting out — material processing — stone dry hanging structure frame fixing — base treatment — mirror frame framework fabrication — dry hanging stone — stainless steel blanking — stainless steel installation — mirror installation — finished surface treatment.

● Connection process between stone and emulsion paint

Distinguish the pasting process, distinguish different materials, and close the mouth completely

Material analysis

  1. The designated stone shall be 20mm, and the stone shall be paved with ordinary portland cement mixed with fine sand or coarse sand or with special marble glue for stone

2. The stone shall be protected on six sides

3. Finish surface treatment, fill, wipe and clean joints with special joint sealant, and use a special protective film for finished product protection

Construction procedure

Preparation — site setting out — material processing — base course treatment — square tube gypsum board base course — cement mortar bonding layer — special binder for stone — paving stone — three bottoms and two sides of the wall (brushing emulsion paint) — finish surface treatment

● Connecting process of stone and wallpaper

01. Connection process between stone and wallpaper (I)

Base course treatment shall be done well in wallpaper construction, and attention shall be paid to the splicing sequence and pattern integrity of wallpaper. It is recommended to make strip treatment for wallpaper and wall tiles. The wall tiles are easy to water, and the wallpaper shall be moisture-proof and waterproof

Material analysis

  1. Customized stone and wallpaper; Galvanized angle steel, galvanized stone dry hanging accessories, 50# corner code

2. The stone is fixed with special AB glue and needs to be protected on six sides. The stone is cut into 10 * 10mm process joint and wallpaper interface

3. Finish the surface treatment, wipe and clean the joints with special sealant, and use a special protective film for finished product protection

Construction procedure

Preparation — site setting out — material processing — stone dry hanging structure frame fixing — base course treatment — wallpaper base course production — dry hanging stone — front treatment — wallpaper pasting — finish treatment

02. Connection process between stone and wallpaper (II)

Material analysis

  1. Select the specified wall tiles, paving, fireproof base course, and wood finish and the wall tiles are paved with ordinary portland cement or mastic

2. Stainless steel strip shall be pressed at the closing of wood facing and wall brick, and the stone shall be protected on six sides

3. Finish surface treatment, fill, wipe and clean joints with special joint sealant, and use a special protective film for finished product protection

Construction procedure

Preparation worksite setting out — material processing — base course treatment — wood veneer base course production — cement mortar bonding layer — wall brick paving — Installation of wood veneer — potting and joint wiping — finish surface treatment

There is no doubt that stone is good, and other materials also have many desirable places. As long as the stone is connected with other materials scientifically and reasonably, the effect can reach the extreme. Well, we’ll write this article here first. For the shortcomings, you are welcome to send an email to sales@sntstone.com Criticism and correction.

Share on facebook
Facebook
Share on twitter
Twitter
Share on linkedin
LinkedIn
sntstone

Don't go away, more surprises!!

Product Inquire

We will contact you within 1 working day, please pay attention to the email with the suffix “@sntstone.com”